Construction Update Week 29

This week we started with finishing the first quay, of which two will be realized on the ALC site. First the quay will be flattened, after which it will be paved. The pouring of the piles is progressing quickly too. We’re now at number 104 of 327 piles. That means 32%! The driving of the piles also continues at a rapid pace. Of the 5555 piles, 3590 are in the ground which amounts to 65%.