Construction Update Week 36

New week, new construction update!


This week a lot has happened and changed visually. Across the entire width of the building, 2 rows of columns have been placed, and the first layer of 2 of the 4 elevator cores has been constructed. The floor is now being placed over these columns. After this we can start using the stairs! A lot of work has been done at the quay too. The dam wall on the east side quay has already been trembled for 95%.


Less visible but equally important: the driving of the piles still continues! 4808 piles have been driven so far, which means we’re at 86% of the total. Only 792 piles left..


Share on facebook
Share on twitter
Share on linkedin

WIJ GEBRUIKEN COOKIES

Om het gebruik van de website te analyseren en het gebruiksgemak te verbeteren.