New week, new construction update!
This week a lot has happened and changed visually. Across the entire width of the building, 2 rows of columns have been placed, and the first layer of 2 of the 4 elevator cores has been constructed. The floor is now being placed over these columns. After this we can start using the stairs! A lot of work has been done at the quay too. The dam wall on the east side quay has already been trembled for 95%.
Less visible but equally important: the driving of the piles still continues! 4808 piles have been driven so far, which means we’re at 86% of the total. Only 792 piles left..