Construction Update Week 39

The last piles!


This week was all about further building up the prefab. The first floor panels of the next stories were partly installed, which means we’re getting closer and closer to the top! Furthermore, the last piles of the building were driven this week. The only piles left are those of the bypass. Next week we’ll get back to you with a new construction update!