Construction Update Week 46

The first two concrete cores for the stairs and elevators have reached the level of the first office floor at 27 meter. The wide plane floors and precast concrete T-pieces around the dock levellers at ground level have been placed. In the north facade, the steel profiles between the concrete columns have been set, so that the concrete sandwich facade panels can be placed above the T-pieces. In addition, this week a third construction crew started, so that even more precast elements can be placed simultaneously.