Construction Update Week 47

In the north facade, the precast concrete facade elements around the docks have been placed. All concrete columns on the north side have reached the office floors at a height of 27 meters, and the placement of the fourth row of columns has been started. This week, also the first foundations of the parking layers and the loading deck have been poured!

We have great news… The contractor has completed the first BREEAM audit with a high score! A great achievement in terms of our sustainability ambition!