Last week, several developments took place. For example, 4 of the 5 concrete cores have reached the floor of the office floors at a height of 27 metres. Also this week, the first structural steel beams for the floors of the office floors have been placed and a start has been made with the placement of storey floors in the next nave of the logistics halls.