For two of the three logistics halls, the concrete columns have reached the full depth of the halls at ground level, and the steel structure on the first floor of these halls is now 50% complete. In addition, a start has been made with the foundations of the last zone of the parking levels and the hollow-core slabs of the first two office floors have been placed.