The last weeks we worked hard again and the results are impressive. The floor of hall 3 has been sealed, the air installation of the first office floor has been completed and work has continued on the installation of the pillars of the office facade.

In addition, the columns of the circulation system at the northeast corner have been placed, the elevator shafts on the north side have been poured, the piles for the porter’s lodge have been driven and the entire drive of the circulation system on the east side is almost complete.

Also, the balustrades at the mezzanine level of Hall 1 and the façade panels on the south side of Hall 1 have been installed. Then the last but certainly not the least development of this week, the overhead doors on the second floor of hall 1 have been installed.