Construction Update Week 17
The highest point has been reached with the installation of the first channel plates of the roof of the office
April 29, 2022

Construction Update Week 8
Despite several storms, there is no damage and the contractor has been able to continue building undisturbed. As a result,
February 28, 2022

Construction Update Week 6
For two of the three logistics halls, the concrete columns have reached the full depth of the halls at ground
February 14, 2022

Construction Update Week 5
Last week, we started both with the columns of the office floors and with the construction of the site drainage.
February 3, 2022

Construction Update Week 4
Various concrete and fire walls of the lower logistic halls have been placed, this in combination with the concrete floors
January 28, 2022

Construction Update Week 3
The concrete floor of the future roof garden is now largely complete! In addition, the first concrete wall panels around
January 19, 2022